[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892769,579,1,"单选题","关于土方开挖的一般要求，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确保设计的开挖轮廓尺寸",false,{"key":16,"text":17,"correct":18},"B","应依据设计确定开挖顺序，开挖顺序包括自上而下、自下而上和上下同时开挖",true,{"key":20,"text":21,"correct":14},"C","防止地表水和地下水影响开挖作业",{"key":23,"text":24,"correct":14},"D","制订合理的边坡支护方案，确保施工安全","土方开挖一般要求包括：①在进行土方开挖施工之前，还应根据所要求的施工工期，制订切实可行的施工方案。②严格执行设计图纸和相关施工的各项规范，确保施工质量。③做好测量、放线、计量等工作，确保设计的开挖轮廓尺寸。④对开挖区域内妨碍施工的建筑物及障碍物，应有妥善的处置措施。⑤切实采取开挖区内的截水、排水措施，防止地表水和地下水影响开挖作业。⑥开挖应自上而下进行。如某些部位确需上、下同时开挖，应采取有效的安全技术措施。严禁采用自下而上的开挖方式。⑦充分利用开挖弃土，尽量不占或少占农田。⑧慎重确定开挖边坡，制订合理的边坡支护方案，确保施工安全。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]