[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892766,579,1,"单选题","混凝土铺料的允许间隔时间应按照（ ）确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土初凝时间",false,{"key":16,"text":17,"correct":14},"B","混凝土温控要求",{"key":19,"text":20,"correct":21},"C","混凝土初凝时间和混凝土温控要求两者中较小值确定",true,{"key":23,"text":24,"correct":14},"D","混凝土浇筑温度","混凝土铺料允许间隔时间是指混凝土自拌和楼出机口到覆盖上层混凝土为止的时间。应按照混凝土初凝时间和混凝土温控要求两者中较小值确定。混凝土温控允许间隔时间，根据混凝土浇筑温度计算确定。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]