[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892762,579,1,"单选题","关于地下厂房洞室群开挖，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地下厂房开挖分层高度在6～8m范围内",false,{"key":16,"text":17,"correct":14},"B","地下厂房洞室群中洞室采用立体作业为主，平面作业为辅",{"key":19,"text":20,"correct":14},"C","一般每方混凝土中钢纤维添加量为70～80kg",{"key":22,"text":23,"correct":24},"D","厂房顶拱层的开挖高度一般在7～10m范围内",true,"A项，地下厂房开挖分层应根据施工通道与地下厂房的结构和施工设备能力综合研究确定，通常分层高度在6～10m范围内。B项，地下厂房洞室群中洞室采用立体、平面交叉作业，施工中既相互联系又相互制约。C项，根据地质条件和部位的重要程度采用不同的支护方法，如喷素混凝土、钢筋网喷混凝土、钢纤维喷混凝土或聚丙烯纤维喷混凝土等。其中，钢纤维混凝土是在混凝土拌和时加入钢纤维，为防止钢纤维结成团，一般用人工均匀撒入拌和机。一般每方混凝土中钢纤维添加量为70～85kg。D项，厂房顶拱层的开挖高度应根据开挖后底部不妨碍吊顶牛腿锚杆的施工和影响多壁液压台车发挥最佳效率来确定，开挖高度一般在7～10m范围内。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]