[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892744,579,1,"单选题","固定式启闭机安装时，基础螺栓及支撑垫板埋设完毕后应进行的下一步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装门架",false,{"key":16,"text":17,"correct":18},"B","安装机架",true,{"key":20,"text":21,"correct":14},"C","安装轨道",{"key":23,"text":24,"correct":14},"D","安装保护元件","固定式启闭机的一般安装程序是：①埋设基础螺栓及支撑垫板；②安装机架；③浇筑基础二期混凝土；④在机架上安装提升机构；⑤安装电气设备和保护元件；⑥连接闸门做启闭机操作试验，使各项技术参数和继电保护值达到设计要求。移动式启闭机的一般安装程序：①轨道安装；②门架安装；③调试与负荷试验。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]