[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892712,579,1,"单选题","输变电工程属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业项目",true,{"key":16,"text":17,"correct":18},"B","城（集）镇部分",false,{"key":20,"text":21,"correct":18},"C","工业企业",{"key":23,"text":24,"correct":18},"D","预备费","专业项目恢复改建补偿包括铁路工程、公路工程、库周交通工程、航运工程、输变电工程、电信工程、广播电视工程、水利水电工程、国有农（林、牧、渔）场及文物古迹和其他项目等。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]