[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892708,579,1,"单选题","联合试运转费不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","消耗的燃料、动力、材料及机械使用费",false,{"key":16,"text":17,"correct":14},"B","工具用具购置费",{"key":19,"text":20,"correct":14},"C","施工单位参加联合试运转人员的工资",{"key":22,"text":23,"correct":24},"D","工程建设监理费",true,"联合试运转费指水利工程的发电机组、水泵等设备安装完毕，在竣工验收前，进行整套设备带负荷联合试运转期间所需的各项费用。其主要包括联合试运转期间所消耗的燃料、动力、材料及机械使用费，工具用具购置费，施工单位参加联合试运转人员的工资等。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]