[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892705,579,1,"单选题","下列各项中，不属于基本预备费范围的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","验收结束时进行恢复导致的费用增加",false,{"key":16,"text":17,"correct":14},"B","设计变更导致的费用增加",{"key":19,"text":20,"correct":14},"C","不可抗力导致的费用增加",{"key":22,"text":23,"correct":24},"D","材料设备价格上涨导致的费用增加",true,"基本预备费通常由以下原因导致：①设计变更导致的费用增加；②不可抗力导致的费用增加；③隐蔽工程验收时发生的挖掘及验收结束时进行恢复所导致的费用增加。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]