[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892704,579,1,"单选题","为解决在工程项目建设过程中，因人工工资、材料和设备价格上涨，以及费用标准调整而增加的投资的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",false,{"key":16,"text":17,"correct":18},"B","价差预备费",true,{"key":20,"text":21,"correct":14},"C","材料补差",{"key":23,"text":24,"correct":14},"D","暂列金额","价差预备费主要为解决在工程项目建设过程中，因人工工资、材料和设备价格上涨，以及费用标准调整而增加的投资。费用内容包括：人工、材料、施工机械的价差费，建筑安装工程费及工程建设其他费用调整，利率、汇率调整等增加的费用。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]