[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892698,579,1,"单选题","夜间施工增加费属于建筑及安装工程费中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费",true,{"key":16,"text":17,"correct":18},"B","间接费",false,{"key":20,"text":21,"correct":18},"C","规费",{"key":23,"text":24,"correct":18},"D","企业管理费","直接费指建筑安装工程施工过程中直接消耗在工程项目上的活劳动和物化劳动，由基本直接费、其他直接费组成。其中，其他直接费包括冬雨季施工增加费、夜间施工增加费、特殊地区施工增加费、临时设施费、安全生产措施费。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]