[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892693,579,1,"单选题","（ ）阶段发生的勘察设计费属于工程勘测设计费。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":18},"B","环境保护设计",false,{"key":20,"text":21,"correct":18},"C","征地移民设计",{"key":23,"text":24,"correct":18},"D","水土保持设计","工程勘测设计费指工程从项目建议书开始至以后各设计阶段发生的勘测费、设计费和为勘测设计服务的常规科研试验费。不包括工程建设征地移民设计、环境保护设计、水土保持设计各设计阶段发生的勘测设计费。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]