[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892689":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892689,579,1,"单选题","对于一些招标文件，如果发现工程范围不明确，条款不清楚或不公正，或技术规范要求过于苛刻时，则要在充分估计投标风险的基础上，按（ ）处理。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不平衡报价法",false,{"key":16,"text":17,"correct":14},"B","增加建议方案",{"key":19,"text":20,"correct":14},"C","无利润报价",{"key":22,"text":23,"correct":24},"D","多方案报价法",true,"对于一些招标文件，如果发现工程范围不明确，条款不清楚或不公正，或技术规范要求过于苛刻时，则要在充分估计投标风险的基础上，按多方案报价法处理。即按原招标文件报一个价，然后提出，如某条款变动，报价可降低，由此可报出一个较低的价。这样可以降低总价，吸引招标人。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]