[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892687,579,1,"单选题","关于不平衡报价的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够早日结账收款的项目可适当提高单价",false,{"key":16,"text":17,"correct":14},"B","预计今后工程量会增加的项目，单价适当提高",{"key":19,"text":20,"correct":21},"C","设计图纸不明确，可以降低单价",true,{"key":23,"text":24,"correct":14},"D","如果工程分标，该暂定项目也可能由其他投标人施工时，则不宜报高价","设计图纸不明确，估计修改后工程量要增加的，可以提高单价；而工程内容说明不清楚的，则可适当降低单价，待澄清后可再要求提价。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]