[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892685,579,1,"单选题","其他项目清单，暂列预留金一项，编制人可根据招标工程具体规定进行补充，一般由（ ）按估算金额确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人",true,{"key":16,"text":17,"correct":18},"B","评标委员会",false,{"key":20,"text":21,"correct":18},"C","投标人",{"key":23,"text":24,"correct":18},"D","政府管理部门","其他项目清单，暂列预留金一项，编制人可根据招标工程具体规定进行补充，一般由招标人按估算金额确定。零星工作项目清单，编制人应根据招标工程具体情况，对工程实施过程中可能发生的变更或新增加的零星项目，列出人工（按工种）、材料（按名称和规格）、机械（按名称和型号规格）的计量单位，并随工程量清单发至招标人，其单价由投标人确定。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]