[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892683,579,1,"单选题","（ ）按招标设计图示衬砌钢板外缘全周长乘以回填灌浆钢板衬砌段长度计算的有效灌浆面积计量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","高压钢管回填灌浆",true,{"key":16,"text":17,"correct":18},"B","隧洞回填灌浆",false,{"key":20,"text":21,"correct":18},"C","岩石层帷幕灌浆",{"key":23,"text":24,"correct":18},"D","岩石层固结灌浆","高压钢管回填灌浆按招标设计图示衬砌钢板外缘全周长乘以回填灌浆钢板衬砌段长度计算的有效灌浆面积计量。连接灌浆管、检查孔回填灌浆、浆液废弃、灌浆操作损耗等所发生的费用，应摊入有效工程量的工程单价中。钢板预留灌浆孔封堵不属于回填灌浆的工作内容，应计入压力钢管的安装费中。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]