[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892682,579,1,"单选题","关于砌筑工程的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","砌体拆除按招标设计图示尺寸计算的拆除体积计量",false,{"key":16,"text":17,"correct":18},"B","砌筑操作损耗不应摊入有效工程量的工程单价中",true,{"key":20,"text":21,"correct":14},"C","砌体砂浆抹面按招标设计图示尺寸计算的有效抹面面积计量",{"key":23,"text":24,"correct":14},"D","施工过程中的超砌量、施工附加量应摊入有效工程量的工程单价中","砌体拆除按招标设计图示尺寸计算的拆除体积计量，砌体砂浆抹面按招标设计图示尺寸计算的有效抹面面积计量，其他项目按招标设计图示尺寸计算的有效砌筑体积计量。施工过程中的超砌量、施工附加量、砌筑操作损耗等所发生的费用，应摊入有效工程量的工程单价中。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]