[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892673,579,1,"单选题","以下计算公式错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工费＝定额劳动量（工日）×人工预算单价（元\u002F工日）",false,{"key":16,"text":17,"correct":14},"B","料费＝定额材料用量×材料预算单价（或材料基价）",{"key":19,"text":20,"correct":21},"C","税金＝（直接费＋利润＋材料价差＋未计价材料费）×税率",true,{"key":23,"text":24,"correct":14},"D","材料价差＝∑[定额材料消耗量×（材料预算价格－材料基价）]","税金的计算公式为：税金＝（直接费＋间接费＋利润＋材料价差＋未计价材料费）×税率。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]