[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892665,579,1,"单选题","关于竣工验收阶段的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","水利工程按照设计文件所规定的内容建成以后，在办理竣工验收以前，必须进行试运行",false,{"key":16,"text":17,"correct":14},"B","竣工验收的目的是全面考核建设成果，检查设计和施工质量",{"key":19,"text":20,"correct":21},"C","竣工验收包括单位工程验收和整个工程项目的全部验收",true,{"key":23,"text":24,"correct":14},"D","对于大型工程，因建设时间长或建设过程中逐步投产，应分批组织验收","竣工验收程序，一般分两个阶段：单项工程验收和整个工程项目的全部验收。对于大型工程，因建设时间长或建设过程中逐步投产，应分批组织验收。验收前，项目法人要组织设计、施工等单位进行初验并向主管部门提交验收申请，根据国家和部颁验收规程，组织验收。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]