[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892661":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892661,579,1,"单选题","（ ）是对水利工程实行静态控制、动态管理的基础。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","《水利工程设计概（估）算编制规定》",true,{"key":16,"text":17,"correct":18},"B","《水利工程概预算补充定额》",false,{"key":20,"text":21,"correct":18},"C","《水利工程施工机械台时费定额》",{"key":23,"text":24,"correct":18},"D","《水利水电设备安装工程预算定额》","《水利工程设计概（估）算编制规定》主要用于在前期工作阶段确定水利工程投资，是编制和审批水利工程设计概（估）算的依据，是对水利工程实行静态控制、动态管理的基础。建设实施阶段，本规定是编制工程标底、投标报价文件的参考标准，施工企业编制投标文件时可根据企业管理水平，结合市场情况调整相关费用标准。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]