[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892660,579,1,"单选题","以下不属于《水利水电设备安装工程概算定额》内容的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","电气设备安装",false,{"key":16,"text":17,"correct":14},"B","水轮发电机安装",{"key":19,"text":20,"correct":21},"C","钻孔灌浆",true,{"key":23,"text":24,"correct":14},"D","起重设备安装","《水利水电设备安装工程概算定额》包括水轮机安装、水轮发电机安装、大型水泵安装、进水阀安装、水力机械辅助设备安装、电气设备安装、变电站设备安装、通信设备安装、起重设备安装、闸门安装、压力钢管制作及安装共十一章以及附录。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]