[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892659,579,1,"单选题","鉴于概算定额尚未颁布，工程概算单价应采用预算定额编制，考虑概算工作的深度和精度以及施工中允许的超挖、超填量，合理的施工附加量等的合理消耗，单价乘以（ ）扩大系数。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2%",false,{"key":16,"text":17,"correct":14},"B","3%",{"key":19,"text":20,"correct":14},"C","4%",{"key":22,"text":23,"correct":24},"D","5%",true,"鉴于概算定额尚未颁布，工程概算单价应采用预算定额编制，考虑概算工作的深度和精度以及施工中允许的超挖、超填量，合理的施工附加量等的合理消耗，单价乘以5%扩大系数。新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com故编制概（估）算时，工程量计算中一般不应再计入这三项工程量。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]