[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892658,579,1,"单选题","关于混凝土地下连续墙的成槽和混凝土浇筑工程量的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土地下连续墙的成槽和混凝土浇筑工程量应分别计算",false,{"key":16,"text":17,"correct":14},"B","成槽工程量按不同墙厚、孔深和地层以面积计算",{"key":19,"text":20,"correct":21},"C","混凝土浇筑工程量，按不同墙厚和地层以成墙长度计算",true,{"key":23,"text":24,"correct":14},"D","混凝土浇筑和运输的工程量在定额中已进行换算","混凝土地下连续墙的成槽和混凝土浇筑工程量应分别计算。成槽工程量按不同墙厚、孔深和地层以面积计算。混凝土浇筑工程量，按不同墙厚和地层以成墙面积计算，成墙面积即阻水而积，混凝土浇筑和运输的工程量在定额中已进行换算。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]