[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892651,579,1,"单选题","根据《水利水电工程设计工程量计算规定》（SL 328—2005），疏浚工程量的计算（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按设计水下方计量，不计超挖及回淤量",true,{"key":16,"text":17,"correct":18},"B","按实际开挖计量，包含超挖及回淤量",false,{"key":20,"text":21,"correct":18},"C","按设计实体方计量，计入超挖量，不计回淤量",{"key":23,"text":24,"correct":18},"D","按设计开挖量计量，计入超挖量，不计回淤量","",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]