[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892650,579,1,"单选题","枢纽工程对外公路工程量，初步设计阶段应根据不小于（ ）的地形图按设计确定的公路等级提出长度或具体工程量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1∶500",false,{"key":16,"text":17,"correct":14},"B","1∶1000",{"key":19,"text":20,"correct":21},"C","1∶5000",true,{"key":23,"text":24,"correct":14},"D","1∶10000","枢纽工程对外公路工程量，项目建议书和可行性研究阶段可根据1∶50000～1∶10000的地形图按设计推荐（或选定）的线路，分公路等级以长度计算工程量。初步设计阶段应根据不小于1∶5000的地形图按设计确定的公路等级提出长度或具体工程量。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]