[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892649,579,1,"单选题","关于永久工程建筑工程量的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","若采用混凝土立模面系数乘以混凝土工程量计算模板工程量时，不再考虑模板阶段系数",false,{"key":16,"text":17,"correct":18},"B","若采用混凝土含钢率或含钢量乘以混凝土工程量计算钢筋工程量时，需要考虑钢筋阶段系数",true,{"key":20,"text":21,"correct":14},"C","截流工程的工程量阶段系数可取1.25～1.35",{"key":23,"text":24,"correct":14},"D","水利水电工程设计工程量阶段系数表中工程量是工程总工程量","水利水电工程设计工程量阶段系数表中需要注意的有：若采用混凝土立模面系数乘以混凝土工程量计算模板工程量时，不再考虑模板阶段系数。若采用混凝土含钢率或含钢量乘以混凝土工程量计算钢筋工程量时，不再考虑钢筋阶段系数。截流工程的工程量阶段系数可取1.25～1.35。水利水电工程设计工程量阶段系数表中工程量是工程总工程量。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]