[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892646,579,1,"单选题","关于暂列金额，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额是初步设计及概算内难以预料的费用",false,{"key":16,"text":17,"correct":14},"B","暂列金额的使用，必须事先得到监理人的许可并遵循其指示",{"key":19,"text":20,"correct":21},"C","暂列金额包括以计日工方式支付的金额",true,{"key":23,"text":24,"correct":14},"D","监理人可以视需要增加一笔暂列金额","A项，工程预备费指初步设计及概算内难以预料的费用。暂列金额是施工中尚未确定和可能发生的但投标阶段难以估算的费用。B项，暂列金额的使用，必须依据合同规定得到发包人或监理人的事先许可，并应按照监理人的指示，进行暂列金额项目的工作。D项，如果监理人认为需要增加一笔暂列金额时，必须事先得到发包人的同意。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]