[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892645,579,1,"单选题","现场签证工作完成后（ ）内，承包人应按照现场签证内容计算价款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7d",true,{"key":16,"text":17,"correct":18},"B","14d",false,{"key":20,"text":21,"correct":18},"C","28d",{"key":23,"text":24,"correct":18},"D","30d","现场签证工作完成后7d内，承包人应按照现场签证内容计算价款，报送发包人确认后，作为增加合同价款，与进度款同期支付。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]