[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892644,579,1,"单选题","某工程项目合同规定，因人工、材料等价格波动影响合同价时，采用公式 计算差额，调整合同价格。规定定值权重A＝0.15，可调值因子有人工费、水泥、钢材和混凝土，其变值权重分别为0.2、0.1、0.25和0.3。各可调值因子的基本价格指数均为100。工程进展到某月结算时，该月完成合同金额100万元，无其他应扣或应支付款额，各可调值因子的现行价格指数是：人工费110，水泥105，钢材106，混凝土108，则按合同规定该月应调整的价格差额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5.9",false,{"key":16,"text":17,"correct":18},"B","6.4",true,{"key":20,"text":21,"correct":14},"C","8.6",{"key":23,"text":24,"correct":14},"D","13.7","按合同规定该月应调整的价格差额为：",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]