[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892643,579,1,"单选题","为了合理划分发承包双方的合同风险，施工合同中应当约定一个基准日，对于招标工程，一般以（ ）前的第28天作为基准日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标截止",true,{"key":16,"text":17,"correct":18},"B","中标通知书发出",false,{"key":20,"text":21,"correct":18},"C","施工合同签订",{"key":23,"text":24,"correct":18},"D","施工组织设计批准","为了合理划分发承包双方的合同风险，施工合同中应当约定一个基准日，对于基准日之后发生的、有经验的承包人在招标投标阶段不可能合理预见的风险，应当由发包人承担。对于招标工程，一般以投标截止前的第28天（以招标文件规定的天数为准）作为基准日；对于非招标工程，一般以施工合同签订前的第28天作为基准日。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]