[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},892641,579,1,"单选题","包工包料工程的预付款的支付比例不得低于签约合同价（扣除暂列金额）的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%",true,{"key":16,"text":17,"correct":18},"B","20%",false,{"key":20,"text":21,"correct":18},"C","30%",{"key":23,"text":24,"correct":18},"D","40%","发包人根据工程的特点、工期长短、市场行情、供求规律等因素，招标时在合同条件中约定工程预付款的百分比。包工包料工程的预付款的支付比例不得低于签约合同价（扣除暂列金额）的10%，不宜高于签约合同价（扣除暂列金额）的30%。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]