[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892640,579,1,"单选题","承包人应按工程量清单的要求对总价子目进行分解，并在签订协议书后的（ ）内将各子目的总价支付分解表提交监理工程师审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","30","承包人应按工程量清单的要求对总价子目进行分解，并在签订协议书后的28d内将各子目的总价支付分解表提交监理工程师审批。分解表应标明其所属子目和分阶段需支付的金额。承包人应按批准的各总价子目支付周期，对已完成的总价子目进行计量，确定分项的应付金额列入进度付款申请单中。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]