[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},892638,579,1,"单选题","关于工程计量的方法的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程计量可选择按月或按工程形象进度分段计量，具体计量周期在合同中约定",false,{"key":16,"text":17,"correct":18},"B","水利工程项目除专用合同条款另有约定外，单价子目已完成工程量按天计量",true,{"key":20,"text":21,"correct":14},"C","因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量",{"key":23,"text":24,"correct":14},"D","总价子目的计量周期按批准的支付分解报告确定","工程计量可选择按月或按工程形象进度分段计量，具体计量周期在合同中约定。水利工程项目除专用合同条款另有约定外，单价子目已完成工程量按月计量，总价子目的计量周期按批准的支付分解报告确定。因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。通常区分单价合同和总价合同规定不同的计量方法，若是成本加酬金合同按照单价合同的计量规定进行计量。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]