[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},892636,579,1,"单选题","根据《水利水电工程标准文件》中的合同条款，下列索赔事件中，承包人可以同时获得工期补偿和费用补偿的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人要求承包人提前交付材料和工程设备",false,{"key":16,"text":17,"correct":14},"B","异常恶劣的气候条件",{"key":19,"text":20,"correct":21},"C","发包人原因引起的暂停施工",true,{"key":23,"text":24,"correct":14},"D","不可抗力","A项，发包人要求承包人提前交付材料和工程设备，承包人只能获得费用补偿。B项，异常恶劣的气候条件，承包人只能获得工期补偿。D项，不可抗力，发包人只能获得工期补偿。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]