[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},892633,579,1,"单选题","关于总价子目的分解和计量的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总价子目的计量和支付应以总价为基础，需要根据物价变动因素而进行调整",false,{"key":16,"text":17,"correct":14},"B","承包人应按建设单位的要求对总价子目进行分解",{"key":19,"text":20,"correct":14},"C","建设单位对承包人提交的上述资料进行复核",{"key":22,"text":23,"correct":24},"D","总价子目的工程量是承包人用于结算的最终工程量",true,"A项，总价子目的计量和支付应以总价为基础，不因物价变动因素而进行调整。承包人实际完成的工程量，是进行工程目标管理和控制进度付款的依据。B项，承包人应按工程量清单中的要求对总价子目进行分解，并在签订协议书后的28d内将各子目的总价支付分解表提交监理工程师审批。C项，监理工程师对承包人提交的上述资料进行复核，以确定分阶段实际完成的工程量和工程形象刚示。",{"id":6,"name":27,"category":28,"favorite":29},"[水利工程]建设工程计量与计价实务","建筑工程",0]