[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892582":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892582,578,2,"多选题","下列关于移动模架的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按行走方式分为自行式和非自行式",true,{"key":16,"text":17,"correct":18},"B","按导梁形式分为前半跨式、前一跨式、前两跨式导梁",false,{"key":20,"text":21,"correct":14},"C","适用于20～70m跨径的多跨简支和连续梁的就地浇筑",{"key":23,"text":24,"correct":14},"D","主要由主梁导梁系统、模板系统、移位调整系统等组成",{"key":26,"text":27,"correct":18},"E","连续施工时每孔仅在（0.2～0.25）L处设一道纵向工作缝","ACD","移动模架是以移动式桁架为主要支承结构的整体模板支架，可一次完成中小跨径桥一跨梁体混凝土的浇筑，适用于20～70m跨径梁体断面形式基本相同的多跨简支和连续梁的就地浇筑。连续施工时每孔仅在（0.2～0.25）L附近处设一道横向工作缝，浇完一孔后，将移动模架前移到下孔位置。移动模架主要由主梁导梁系统、吊架支撑系统、模板系统、移位调整系统、液压电气系统及辅助设施等部分组成。移动模架结构按行走方式分为自行式和非自行式，按导梁的形式分为前一跨式导梁、前半跨式导梁、前后结合导梁等，按底模的安拆方式分为平开合式、翻转式等，按与箱梁的位置和过孔方式分为上行式（上承式）、下行式（下承式）和复合式三种形式。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]