[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892561":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892561,578,2,"多选题","一般而言，除应急养护以外的养护工程组织实施的程序有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","前期工作",true,{"key":16,"text":17,"correct":14},"B","计划编制",{"key":19,"text":20,"correct":14},"C","工程设计",{"key":22,"text":23,"correct":14},"D","工程施工",{"key":25,"text":26,"correct":27},"E","工程报告",false,"ABCD","公路养护工作的组织实施应当依照有关法律、法规和规定，各类养护工程所涉及的技术服务与工程施工等相关作业，应通过公开招标投标、政府采购等方式选择具备相应技术能力和资格条件的单位承担。一般而言，养护工程应当按照前期工作、计划编制、工程设计、工程施工、工程验收等程序组织实施；应急养护除外。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]