[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892553":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892553,578,2,"多选题","养护工程按照养护目的和养护对象，可以分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预防养护",true,{"key":16,"text":17,"correct":18},"B","集中养护",false,{"key":20,"text":21,"correct":14},"C","修复养护",{"key":23,"text":24,"correct":14},"D","专项养护",{"key":26,"text":27,"correct":14},"E","应急养护","ACDE","养护工程按照养护目的和养护对象，分为预防养护、修复养护、专项养护和应急养护。预防养护是公路整体性能良好但有轻微病害，为延缓性能过快衰减、延长使用寿命而预先采取的主动防护工程。修复养护是公路出现明显病害或部分丧失服务功能，为恢复技术状况而进行的功能性、结构性修复或定期更换，包括大修、中修、小修。专项养护是为恢复、保持或提升公路服务功能而集中实施的完善增设、加同改造、拆除重建、灾后恢复等工程。应急养护是在突发情况下造成公路损毁、中断、产生重大安全隐患等，为较快恢复公路安全通行能力而实施的应急性抢通、保通、抢修。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]