[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892544":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892544,578,2,"多选题","施工机械一般检验的方法和步骤可分为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","外部检验",true,{"key":16,"text":17,"correct":14},"B","空运转试验",{"key":19,"text":20,"correct":21},"C","内部检验",false,{"key":23,"text":24,"correct":14},"D","重载试验",{"key":26,"text":27,"correct":21},"E","联合试运行试验","ABD","做好施工前的准备工作： ①机械的运输。根据运输方式不同可分为陆运、水运和空运。根据公路施工机械的特点，其中陆运是最常用的方法。 ②做好机械的安装工作。安装工作程序可分为以下几个阶段：编制安装工程的施工设计；修筑机械和设备基础；安装主要机械设备和辅助设备；设备调试；试运转与交付使用。 ③做好机械的验收和交付使用工作。应根据机械来源的不同，经过不同的检验和试验，一般检验的方法和步骤可分为外部检验、空运转试验和重载试验。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]