[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892539":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892539,578,2,"多选题","明洞工程应先施工完成，为加速隧道施工创造条件。下列关于明洞工程施工的说法，错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","防水层敷设搭接长度不小于100mm",false,{"key":16,"text":17,"correct":14},"B","边坡松软易坍塌宜采用先拱后墙法",{"key":19,"text":20,"correct":21},"C","仰坡易坍塌时宜由内向外进行施工",true,{"key":23,"text":24,"correct":21},"D","顶部两侧回填的土面高差不得大于0.3m",{"key":26,"text":27,"correct":21},"E","人工填筑拱顶中心回填高度达到0.6m时拆除拱架","CDE","A项，明洞应设置防水层，敷设时应粘贴紧密，相互搭接错缝，搭接长度不小于100mm，并向隧道内拱背延伸不少于0.5m。B项，明洞施工一般采用先墙后拱法。当边坡松软易坍塌及明洞与暗洞衔接时，施工宜采用先拱后墙法。C项，在仰坡暂能稳定的情况下，宜由内向外进行施工；在仰坡易坍塌的情况下，宜先将明洞拱圈浇筑到仰坡脚，再由内向外作洞内拱圈，并确保仰坡稳定。D项，明洞段顶部回填土方应对称分层夯实，每层厚度不得大于0.3m，两侧回填的土面高差不得大于0.5m。E项，在人工填筑时，拱顶中心回填高度达到0.7m以上方可拆除拱架。若使用机械施工回填时，则应在回填土石全部完成后方可拆除拱架。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]