[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892535":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892535,578,2,"多选题","关于灌注水下混凝土，以下说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","水下混凝土配制，粗集料宜选用砾石",false,{"key":16,"text":17,"correct":18},"B","当桩径D＜1.5m时，其坍落度宜为180～220mm",true,{"key":20,"text":21,"correct":14},"C","水下混凝土的灌注时间不得超过首批混凝土的终凝时间",{"key":23,"text":24,"correct":18},"D","首批灌注混凝土的数量应能满足导管首次埋置深度1.0m以上的需要",{"key":26,"text":27,"correct":18},"E","在灌注中，应保持孔内的水头高度，导管的埋置深度宜控制在2～6m","BDE","水下混凝土配制，粗集料宜选用卵石，混凝土可经试验掺入适量缓凝剂，混凝土拌合物应具有良好的和易性。当桩径D＜1.5m时，其坍落度宜为180～220mm；桩径D＞1.5m时，坍落度宜为160～200mm。水下混凝土的灌注时间不得超过首批混凝土的初凝时间，首批灌注混凝土的数量应能满足导管首次埋置深度1.0m以上的需要，其中导管底至桩底距离一般为0.3～0.4m。首批混凝土入孔后，应连续灌注，不得中断。在灌注中，应保持孔内的水头高度，导管的埋置深度宜控制在2～6m，并应随时测探孔内混凝土面的位置，及时调整导管埋深。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]