[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892534":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892534,578,2,"多选题","关于钢筋工程施工，以下说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢筋应具有出厂质量证明书和试验报告单",true,{"key":16,"text":17,"correct":18},"B","进场时主要检查其外观和标志",false,{"key":20,"text":21,"correct":14},"C","钢筋在运输过程中应避免锈蚀、污染或被压弯",{"key":23,"text":24,"correct":14},"D","在工地存放时，应按不同品种、规格，分批分别堆置整齐，不得混杂",{"key":26,"text":27,"correct":18},"E","存放的时间不宜超过3个月","ACD","钢筋应具有出厂质量证明书和试验报告单，进场时除应检查其外观和标志外，尚应按不同的钢种、等级、牌号、规格及生产厂家分批抽取试样进行力学性能检验，检验试验方法应符合现行国家标准的规定。钢筋经进场检验合格后方可使用。钢筋在运输过程中应避免锈蚀、污染或被压弯；在工地存放时，应按不同品种、规格，分批分别堆置整齐，不得混杂，并应设立识别标志，存放的时间不宜超过6个月。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]