[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892528":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892528,578,2,"多选题","隧道地质超前预报方法主要有地质调查法和（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","物理勘探法",true,{"key":16,"text":17,"correct":14},"B","超前导坑法",{"key":19,"text":20,"correct":14},"C","超前钻探法",{"key":22,"text":23,"correct":24},"D","化学勘探法",false,{"key":26,"text":27,"correct":14},"E","水力联系观测法","ABCE","隧道地质超前预报方法主要包括：①地质调查法，适用于各种地质条件隧道超前地质预报，调查内容包括隧道地表补充地质调查和隧道内地质调查。②超前钻探法，超前水平岩芯钻孔，可视为隧道中的微型导坑，可以探测了解隧道开挖工作面前方几十米乃至上百米范围内同岩的地质情况。③物理勘探法，适用于长、特长隧道或地质条件复杂隧道的超前地质预报，主要方法包括弹性波反射法、地质雷达法、陆地声呐法等。④TSP法，适用于各种地质条件，对断层、软硬接触面等面状结构反射信号较为明显。⑤超前导坑法，根据导坑开挖揭露的同岩地质情况，能了解并较准确地判断预测隧道开挖工作面前方相应地段围岩的工程地质及水文地质条件。⑥水力联系观测法，适用于当隧道排水、突涌水对地下水资源或周围建筑（构）物产生重大影响的地质情况。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]