[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892524":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892524,578,2,"多选题","二次衬砌可以与初期支护共同组成复合式衬砌。下列关于二次衬砌施工的说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","仰拱应先于衬砌浇筑完成",true,{"key":16,"text":17,"correct":18},"B","浇筑仰拱从仰拱两侧向中心对称进行",false,{"key":20,"text":21,"correct":14},"C","二次衬砌必须重视模筑混凝土的抗冻性",{"key":23,"text":24,"correct":18},"D","隧道纵向需分段浇筑，分段长度为8～10m",{"key":26,"text":27,"correct":14},"E","全断面开挖隧道应尽量使用混凝土整体衬砌","ACE","AB两项，仰拱应先于衬砌浇筑完成，在施工安排中，应尽快修筑仰拱，以利衬砌结构的整体受力。仰拱断面开挖后应立即检查并浇筑混凝土，浇筑仰拱应采用大样板，并由仰拱中心向两侧对称进行。C项，二次衬砌采用模筑混凝土，模筑混凝土的材料和级配，应符合隧道衬砌的强度和耐久性要求，同时必须重视其抗冻、抗渗和抗侵蚀性。D项，二次衬砌施工时，隧道纵向需分段进行，分段长度一般为8～12m。E项，全断面开挖成形或大断面开挖成形的隧道衬砌施工中，应尽量使用钢模板衬砌台车灌注混凝土整体衬砌。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]