[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892523":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892523,578,2,"多选题","关于新奥法施工，下列说法错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","新奥法施工过程主要是开挖、喷锚、模筑混凝土",false,{"key":16,"text":17,"correct":14},"B","新奥法通过监测控制围岩的变形以充分发挥围岩自承能力",{"key":19,"text":20,"correct":21},"C","初次柔性支护，是在洞身开挖之前必须立即进行的支护工作",true,{"key":23,"text":24,"correct":21},"D","新奥法以喷射混凝土和锚杆作为辅助支护手段",{"key":26,"text":27,"correct":14},"E","装饰是整个隧道贯通之后才进行的","CD","新奥法是以喷射混凝土和锚杆作为主要支护手段，通过监测控制围岩的变形，便于充分发挥围岩的自承能力为基点的施工方法。新奥法的基本理论依据是在利用围岩本身所具有的承载效能的前提下，采用毫秒爆破和光面爆破技术，进行断面开挖施工，并以复合式内外两层衬砌形式来修建隧道的洞身，即以喷射混凝土、锚杆、钢筋网、钢支撑等为其外层支护形式，称为初次柔性支护，是在洞身开挖之后必须立即进行的支护工作。新奥法施工可划分为：开挖、喷锚（初期支护）、模筑混凝土（二次衬砌）和装饰四个过程。其施工过程主要是开挖、喷锚、模筑混凝土三大工序的循环式流水作业。装饰是整个隧道贯通之后才进行的。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]