[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892519":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892519,578,2,"多选题","下列关于斜拉桥施工的说法中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","斜拉桥可看作多跨弹塑性支承连续梁",false,{"key":16,"text":17,"correct":14},"B","湿接缝混凝土浇筑后的养护时间应不少于3天",{"key":19,"text":20,"correct":21},"C","漂浮体系斜拉桥主梁施工期间塔梁应临时固结",true,{"key":23,"text":24,"correct":21},"D","钢主梁制造完成后应在工厂进行试拼装和涂装",{"key":26,"text":27,"correct":21},"E","主梁合龙期间桥面上临时施工荷载应严格控制","CDE","A项，斜拉桥可看作是拉索代替支墩的多跨弹性支承连续梁。B项，各桥面板单元之间的湿接缝应采用微膨胀低收缩混凝土，湿接缝混凝土浇筑后的养护时间应不少于7天。C项，设计为漂浮或半漂浮体系的斜拉桥，在主梁施工期间应使塔梁临时固结。D项，钢主梁制造完成后应在工厂内进行试拼装和涂装，经质量检验合格后方可运至工地现场。E项，主梁合龙施工期间，应对桥面上的临时施工荷载进行严格控制，不得随意施加除合龙施工需要外的其他附加荷载。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]