[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892518,578,2,"多选题","下列关于斜拉桥拉索施工的说法中错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","拉索可在塔端或梁端单端进行张拉",false,{"key":16,"text":17,"correct":14},"B","张拉拉索时应采用专门设计制作的施工平台",{"key":19,"text":20,"correct":21},"C","张拉时应按索塔的顺桥向两侧对称不同步进行",true,{"key":23,"text":24,"correct":21},"D","千斤顶同步之差不得小于油表读数的最小分格",{"key":26,"text":27,"correct":14},"E","设计拉力不同的拉索应按设计规定的索力分级同步张拉","CD","拉索的安装施工应按设计和施工控制的要求进行，在安装和张拉拉索时应采用专门设计制作的施工平台及其他辅助设施进行操作，保证施工安全。拉索可在塔端或梁端单端进行张拉，张拉时应按索塔的顺桥向两侧及横桥向两侧对称同步进行。两侧不对称或设计拉力不同的拉索，应按设计规定的索力分级同步张拉，各千斤顶同步之差不得大于油表读数的最小分格。张拉宜以测定的索力或油压表量值为准，以延伸值做校核。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]