[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892513":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892513,578,2,"多选题","关于桩基和承台施工，下列说法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","桩头预留钢筋上的泥土及鳞锈等应清理干净",true,{"key":16,"text":17,"correct":14},"B","承台基地为软弱土层时，应按设计要求采取措施",{"key":19,"text":20,"correct":14},"C","承台施工前，应进行桩基等隐蔽工程的质量验收",{"key":22,"text":23,"correct":14},"D","沉桩施工方法主要有锤击沉桩、振动沉桩、射水沉桩",{"key":25,"text":26,"correct":27},"E","挖孔灌注桩孔口处应设置高出地面至少200mm的护圈",false,"ABCD","AB项，桩头预留钢筋上的泥土及鳞锈等应清理干净，承台基地为软弱土层时，应按设计要求采取措施，避免在浇筑承台混凝土过程中产生不均匀沉降；C项，承台施工前，应进行桩基等隐蔽工程的质量验收；D项，沉桩的施工方法主要有锤击沉桩、振动沉桩、射水沉桩；E项，挖孔灌注桩孔口处应设置高出地面至少300mm的护圈。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]