[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892512":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892512,578,2,"多选题","关于钻孔灌注桩施工，下列说法错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","护筒埋置深度在旱地宜为2～4m",false,{"key":16,"text":17,"correct":14},"B","首批混凝土入孔后，应连续灌注，不得中断",{"key":19,"text":20,"correct":21},"C","钢筋笼外侧控制保护层厚度的垫块竖向间距为2.5m",true,{"key":23,"text":24,"correct":21},"D","冲击钻进过程中孔内水位应高于护筒底口100mm以上",{"key":26,"text":27,"correct":21},"E","水下混凝土的灌注时间不得超过首批混凝土的终凝时间","CDE","A项，护筒埋置深度在旱地或筑岛处宜为2～4m；B项，首批混凝土入孔后，应连续灌注，不得中断；C项，钢筋笼骨架外侧设置控制保护层厚度的垫块，其间距竖向为2m，横向圆周不得少于4处；D项，冲击钻进过程中，孔内水位应高于护筒底口500mm以上，掏取钻渣和停钻时，应及时向孔内补水，保持水头高度；E项，水下混凝土的灌注时间不得超过首批混凝土的初凝时间，首批灌注混凝土的数量应能满足导管首次埋置深度1.0m以上的需要。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]