[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892511":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892511,578,2,"多选题","下列关于明挖扩大基础施工的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","孔深＞3m时，宜先注浆后插入锚杆",false,{"key":16,"text":17,"correct":18},"B","开挖过程中排水时应不对基坑的安全产生影响",true,{"key":20,"text":21,"correct":18},"C","基底超挖时应清除松动部分，并对基底进行处理",{"key":23,"text":24,"correct":18},"D","坑壁或边坡上有明显出水点时，应设置导管排水",{"key":26,"text":27,"correct":14},"E","扩大基础基底为岩石时，施工前应润湿并浇筑混凝土垫层","BCD","A项，孔深≤3m时，宜用先注浆后插入锚杆工艺，孔深＞3m时，宜先插入锚杆后注浆。注浆应采用孔底注浆法。B项，在开挖过程中进行排水时应不对基坑的安全产生影响，排水困难时，宜采用水下挖基方法。C项，开挖过程中如果超挖，应清除松动部分，并应对基底进行处理。D项，坑壁或边坡上有明显出水点时，应设置导管排水。E项，扩大基础的基底为非黏性土或干土时，施工前应润湿，并浇筑混凝土垫层。基底为岩石时，应用水冲洗干净，且铺一层不低于基础混凝土强度的水泥砂浆。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]