[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892508,578,2,"多选题","下列关于模板、拱架和支架的设计及施工说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","外露面模板板面宜采用胶合板",false,{"key":16,"text":17,"correct":18},"B","模板拆除应先支先拆，后支后拆",true,{"key":20,"text":21,"correct":14},"C","拱架需验算强度、刚度及稳定性",{"key":23,"text":24,"correct":14},"D","模板板面应保证结构物线条流畅",{"key":26,"text":27,"correct":18},"E","大面积混凝土每块模板的面积宜小于10m2","BE","AE两项，外露面的模板板面宜采用钢模板、胶合板。为减少模板的拼缝，对于大面积的混凝土，其每块模板的面积宜大于10m2。B项，根据《公路桥涵施工技术规范》（JTG\u002FTF 50—2011）第5.5.6条规定，模板、支架的拆除应遵循后支先拆、先支后拆的原则顺序进行，墩台的模板宜在其上部结构施工前拆除。C项，在计算荷载作用下，对模板、拱架及支架结构按受力程序分别验算其强度、刚度及稳定性。D项，模板板面之间应平整，接缝严密，不漏浆，保证结构物外露面美观，线条流畅。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]