[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892507":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892507,578,2,"多选题","下列关于路面工程的说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土板达到设计强度30%后，行人方可通行",true,{"key":16,"text":17,"correct":18},"B","沥青混合料的机械摊铺松铺系数为1.15～1.30",false,{"key":20,"text":21,"correct":14},"C","改性沥青混合料一般应在温度降至100℃前结束碾压作业",{"key":23,"text":24,"correct":18},"D","黏层所使用的基层基质沥青等级宜与主层沥青混合料相同",{"key":26,"text":27,"correct":18},"E","路面结构层自下而上依次为：垫层、底基层、基层、面层","AC","A项，混凝土板养护初期，严禁人、畜、车辆通行，在达到设计强度40%后，行人方可通行。在路面养护期间，平交道口应搭建临时便桥。B项，沥青混合料的松铺系数应根据实际的混合料类型，由试铺试压方法或以往实践经验确定；机械摊铺松铺系数1.15～1.30，人工摊铺松铺系数1.20～1.45。C项，改性沥青混合料一般应在温度降至120℃前结束碾压作业。D项，黏层宜采用快裂或中裂乳化沥青、改性乳化沥青，所使用的基层基质沥青等级宜与主层沥青混合料相同。E项，路面结构层自下而上依次为：垫层、底基层、基层、面层。",{"id":6,"name":31,"category":32,"favorite":33},"[交通运输工程]建设工程计量与计价实务","建筑工程",0]